Centaur IPC Holdings South Africa (Pty) Ltd
Name: Transvaal Navigational Collieries (OC4B Pits - Deal 2)
Location: Kriel, Mpumalanga, South Africa
Commodity: Coal rail logistics
Entry date: Jul 2025
Exit date: Aug 2026
Capital Committed: R6,000,000
ROI: 40%
MOIC: 1.4x
IRR: 40%
Model: Revenue-Based Financing (RBF)
Mine stage: Pre-production, resource statement validated
Production: 1,200,000t, RB 2 coal
Operators: Centaur IPC Holdings South Africa
Impact: 40 at the pit, 36 on the wash-plant jobs created
Limited Partners: Gibela Fund
Milestones: Dewatering is at 90% completion, and mining has commenced on the fringe blocks of the OC4B Pit.
Challenges: Dewatering took longer than expected, by 3 months.